Penalty Clauses in Italian Contracts: When the Court Can Reduce Them - Panato Law Firm — Verona

Foreign businesses sometimes rely on a high contractual penalty as a deterrent. In Italy that figure is not always the final word.

A penalty clause fixes in advance the amount due for non-performance or delay, and is owed regardless of proof of damage. Further damages can be claimed only if expressly agreed (art. 1382 c.c.).

The judge may reduce the penalty fairly if the main obligation has been partly performed or if the amount is manifestly excessive, considering the creditor's interest in performance (art. 1384 c.c.).

At a glance

  • Due without proof of damage.
  • Extra damages only if the contract says so.
  • Can be reduced if manifestly excessive.
  • Also reduced when the obligation was partly performed.

What to do

  1. Calibrate the penalty to a realistic estimate of loss.
  2. State expressly whether further damages remain claimable.
  3. Keep evidence of your interest in timely performance.

Legal basis: Arts. 1382 and 1384 Italian Civil Code.

This note is general information and does not replace advice on a specific case.

Do you need legal assistance or a free estimate?

Author: Avv. Marco Panato


Avv. Marco Panato -

Avv. Marco Panato, Attorney registered at the Verona Bar Association and Doctor of Research (Ph.D.) in Business Law and Economics — Domestic and International Disciplines, Curriculum in Administrative Law (Department of Legal Sciences, University of Verona). Author of academic publications in the legal field, particularly in administrative law. He also delivers lectures and advanced professional training.